Log in

Government

Litchfield Park seeks bids for perimeter wall project

$800,000 budgeted for reconstruction

Posted 9/24/20

Litchfield Park is rebuilding a wall.

You must be a member to read this story.

Join our family of readers for as little as $5 per month and support local, unbiased journalism.


Already have an account? Log in to continue.

Current print subscribers can create a free account by clicking here

Otherwise, follow the link below to join.

To Our Valued Readers –

Visitors to our website will be limited to five stories per month unless they opt to subscribe. The five stories do not include our exclusive content written by our journalists.

For $6.99, less than 20 cents a day, digital subscribers will receive unlimited access to YourValley.net, including exclusive content from our newsroom and access to our Daily Independent e-edition.

Our commitment to balanced, fair reporting and local coverage provides insight and perspective not found anywhere else.

Your financial commitment will help to preserve the kind of honest journalism produced by our reporters and editors. We trust you agree that independent journalism is an essential component of our democracy. Please click here to subscribe.

Sincerely,
Charlene Bisson, Publisher, Independent Newsmedia

Please log in to continue

Log in
I am anchor
Government

Litchfield Park seeks bids for perimeter wall project

$800,000 budgeted for reconstruction

Posted

Litchfield Park is rebuilding a wall.

The city is asking construction companies to submit bids for phase five of its ongoing wall reconstruction project.

City Engineer Woody Scoutten said via email Thursday, Sept. 24, the city budgeted up to $800,000 for the project, which will include removing 3,150 lineal feet of existing concrete block wall on the east side of Litchfield Road between the golf cart underpass and Bird Lane and replacing it with a new 8-foot-tall concrete block wall.

Cost of previous phases, completed between May 2007 and December 2017, totaled $3.82 million. Cost information for the first phase, completed in 2004, was not available, Mr. Scoutten said.

READ: Litchfield Park eyes $9.9 million on capital projects over five years

Bids are due by 10 a.m. Thursday, Nov. 5. Companies planning to submit bids must attend a mandatory meeting scheduled for 1 p.m. Monday, Oct. 26, via Zoom. To register for the meeting, visit litchfield-park.org and click on the Bids & RFPs tab.

For more information and questions, email Mr. Scoutten at wscoutten@litchfield-park.org or call 623-889-6208.